Menu
Sat, 23 November 2024

Newsletter sign-up

Subscribe now
The House Live All
Collaboration is key for a smooth transition to Great British Rail Partner content
By Transport UK
Transport
Why addressing gender equality is key to meeting our net-zero ambitions Partner content
By WSP
Port of Dover party conference season unites politicians on plan for economic growth Partner content
Transport
Recruiting the next generation of train drivers Partner content
By Rail Safety and Standards Board (RSSB)
Transport
Why UK airspace needs to be part of Labour’s infrastructure revolution Partner content
By NATS
Transport
Press releases
By Luton Rising
By Luton Rising

Network Rail to upgrade West Coast line

Network Rail

2 min read Partner content

Four major junctions will be replaced on the West Coast Main Line this summer, Network Rail has announced.

In addition, three miles of track re-laid as part of an £18m improvement scheme.

6,600 new railway sleepers will be laid and 21,500 tonnes of ballast will be poured.

The work will improve the reliability of the infrastructure and the punctuality of train services on Britain's busiest mixed-use railway line and will be carried out over nine days from Saturday 13 July to Sunday 21 July.

Over an 18 mile stretch of line near Wigan during this time, trains will be unable to use the Warrington to Preston section of the route.

Train operators are developing timetables for alternative services, which will be publicised and available through rail journey planning and train company websites.

A spokesman for Network Railsaid:

“We would normally carry out work of this kind over a number of Bank Holiday weekends, meaning repeated replacement train services.

“By carrying out the work in a nine-day continuous spell this summer, we expect to complete the replacement of the four junctions around 16 months earlier, thereby avoiding disrupting rail travel plans for many weekends and nine bank holidays over the next two years.

“There is never a good time to carry out major work on such a busy route and after careful discussion with the train operators and industry partners, it became apparent that undertaking this vital investment in nine consecutive days in July would, overall, cause less disruption.

“Train services are quieter at this time and fewer people are expected to experience changes to their travel plans.”

The improvements will mean train services can run at up to 75 mph over the four upgraded junctions – Golborne Junction, Bamfurlong, Wigan Springs Branch, Balshaw Lane Junction.

PoliticsHome Newsletters

Get the inside track on what MPs and Peers are talking about. Sign up to The House's morning email for the latest insight and reaction from Parliamentarians, policy-makers and organisations.

Categories

Transport
Podcast
Engineering a Better World

The Engineering a Better World podcast series from The House magazine and the IET is back for series two! New host Jonn Elledge discusses with parliamentarians and industry experts how technology and engineering can provide policy solutions to our changing world.

NEW SERIES - Listen now